Customise consent preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site.... 

Always active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Back to projects

The Mall

Location

45 Selborne Walk

Sector

retail

Nature

dangerous structure remediation and rebuilding of the shopping centre

Value

£ in excess of £9 million

Employer

Capital & Regional Plc

Delivered by

de-contracting logo de-construct logo

Project details

Following a devastating fire at The Mall in Walthamstow, the DE Group were called upon, alongside the emergency services and forensics teams, to assess the structure and make safe the dangerous conditions.

We were then tasked to create separation between the undamaged areas of the mall and the resultant construction zone to allow the partial re-opening of the centre.

Following a successful partial re-opening and a period of close collaborative working with the client’s professional team, insurers and loss adjusters, De Group Contracting were awarded the contract for extensive re-construction and refurbishment works. The client and the centre management team were delivered a swift, seamless transition from disaster recovery back to a fully operational shopping centre.

The works were procured through a hybrid arrangement, combining negotiation with supply chain and a competitive tender element in order to maximise the balance on construction cost and programme time.

Scope of works

The scope of works to fully re-open the shopping mall comprised:

  • dangerous structure remediation
  • MEP services
  • temporary works
  • food court
  • new roof structure and coverings
  • new façades to entrances
  • rebuilding of external walls
  • lifts and escalators
  • internal mall finishes
  • new guest amenities & WCs
  • new atrium glazing and internal finishes
  • new management suite and security offices.